GAME Warehouse Racking Removal, Basingstoke

Racking takedown at a 100,000 sq ft warehouse, completed in three weeks against a four-week deadline. Ten articulated lorries removed the equipment, with most of the racking delivered directly to its next installation.

Discuss Your Racking ProjectView the Project Specification

Rack It Stack It

  • 100,000sq ftWarehouse unit
  • 3weeksCompleted against a four-week deadline
  • 7peopleOn-site team
  • 10artic loadsRacking removed

A defined role in a major dilapidations project

Rack It Stack It carried out the racking takedown element of the dilapidations project at the former GAME distribution warehouse on Telford Road, Houndmills Industrial Estate, Basingstoke.

The approximately 100,000 sq ft unit contained a substantial mix of STOW, Link 51 and Apex racking. Our scope covered dismantling and removing the racking, taking down the anti-collapse mesh, and decommissioning and disposing of the associated four-level sprinkler system.

Working within the demolition contractor’s site arrangements, our seven-person team completed the work in three weeks, one week ahead of the four-week deadline.

Background: GAME’s Basingstoke head office and warehouse, the company’s headquarters for more than 20 years, were reported to be closing in April 2025.

Project at a glance

Site
Former GAME head office and distribution warehouse
Location
Houndmills Industrial Estate, Telford Road, Basingstoke, Hampshire RG21 6YJ
Unit
Approximately 100,000 sq ft
Our scope
Racking takedown within a wider dilapidations project: racking dismantled and removed, anti-collapse mesh taken down, and the associated four-level sprinkler system decommissioned and disposed of
Programme
Completed in three weeks, against a four-week deadline
Team
Seven people on site
Removal
Ten articulated lorry loads
Reuse
The majority of the racking delivered directly to a new customer’s installation
Wide view of the main hall of the former GAME warehouse in Basingstoke with racking frames along the right-hand wall and a forklift on the floor.
The main hall: a tall container-storage structure on the left, racking frames along the right-hand wall and a mezzanine at the far end.

The equipment to handle 12-metre racking

The STOW installation formed the largest part of the racking schedule, with frames reaching 12 metres and heavy-duty beams measuring up to 3.7 metres.

Rack It Stack It organised the plant hire for the works: two 16m scissor lifts, a specialist scissor lift for removing the anti-collapse mesh, and two reach trucks. This gave the team the access and handling equipment required for the racking works.

Plant for the racking works

Scissor lifts
2 × 16m scissor lifts
Specialist access
1 × specialist scissor lift for anti-collapse mesh
Reach trucks
2 × reach trucks
Plant hire
Organised by Rack It Stack It
A raised scissor lift and a reach truck on the open floor of the main hall in the former GAME warehouse.
A raised scissor lift and a reach truck in the main hall.
Tall blue pallet racking frames and beams seen from floor level in the former GAME warehouse, Basingstoke.
Blue upright frames and beam levels in the high-bay area, seen from floor level.

Working to the demolition site’s rules

Every member of the team completed the required site induction and worked to the site rules, with PPE worn throughout the works. No instances of failure to follow those rules were reported.

The demolition company’s site manager specifically praised the team’s attitude, behaviour and efficiency on site.

Ten artic loads, completed a week ahead of programme

The racking was dismantled, removed and loaded onto ten articulated lorries. The takedown scope was completed in three weeks, against the four weeks available.

That early completion delivered our part of the dilapidations programme with a week to spare. It is the kind of industrial racking takedown covered by our pallet racking removal and dismantling service.

Blue racking beams stacked on the warehouse floor in front of numbered high-bay racking runs.
Blue beams stacked on the floor in front of the numbered high-bay runs.
Blue racking upright frames stacked flat along the length of a curtain-sided articulated trailer.
Blue upright frames stacked flat on a curtain-sided trailer, running almost its full length.

From takedown straight to the next installation

The majority of the pallet racking already had its next destination arranged. It travelled directly from Basingstoke to a new customer’s warehouse for reinstallation, rather than returning to our yard for storage and a later onward delivery.

  1. 1Basingstoke takedown
  2. 2Direct delivery
  3. 3New warehouse installation
Route used for the majority of the recovered racking.

After completing the takedown, the same team moved on to install the racking at the receiving site. This connected the removal and installation stages, keeping the equipment in use and avoiding an intermediate storage stop for that stock.

Direct delivery avoided the intermediate journey to our yard and the subsequent onward delivery for the racking sent straight to the new installation. The reuse benefit is as simple as it sounds: existing racking went back into service.

A 70% saving for the receiving customer

By choosing the recovered pallet racking, the receiving customer saved 70% compared with buying new pallet racking.

For this project, reuse connected two requirements: removing racking from the former GAME warehouse and supplying it for another customer’s installation.

  • 70% savingFor the receiving customer, compared with buying new pallet racking.
  • Direct reuseMost of the racking went straight from Basingstoke to its next installation.

The saving relates to this project: the recovered racking compared with buying new pallet racking. It is not a general discount, and every project is priced individually.

If reuse could suit your own warehouse, see our pallet racking bays, including used systems, or how a used pallet racking installation is planned.

Project specification: three systems, recorded separately

The racking schedule records three systems: heavy-duty STOW racking, Link 51 M-duty and Apex UK 12. The largest section comprised 252 STOW frames measuring 12,000 × 1,100mm. Alongside this were 150 four-metre frames across the Link 51 and Apex systems. Beam lengths ranged from 1,850mm to 3,700mm, with mesh decking recorded for both of the lower-height systems.

In total the schedule lists 402 upright frames, 3,696 individual beams and 828 mesh decking panels, with the tallest recorded frames at 12 metres. Each manufacturer’s racking is listed on its own, because components from different manufacturers are not designed to be mixed.

Component totals by system
System Frames Beams Mesh decking panels
STOW 252 2,868 none recorded
Link 51 M-duty 72 396 396
Apex UK 12 78 432 432
Total 402 3,696 828

These are component counts: frames and individual beams, not bays or pallet positions. The 828 mesh decking panels are the horizontal decks that sit on the beams; the anti-collapse mesh taken down during the works is separate and is not counted in this schedule. Frame sizes are height × depth. Recorded project specifications; loading suitability depends on the complete configuration and supporting design information, and the UDL figures are not a loading certification.

STOW 12-metre frames and the largest component schedule

STOW accounted for the largest part of the recorded inventory, with 252 frames and 2,868 beams. The frames measured 12 metres high by 1,100mm deep, with a recorded 100mm face and the system reference “Stow 16”.

Most beams were 3,700mm long, supplemented by 2,800mm and 2,000mm lengths. Keeping those groups distinct preserves the differences in section size and recorded loading information.

STOW: components recorded in the project schedule
Component Quantity Size Detail Recorded UDL
Frames 252 12,000 × 1,100mm (height × depth) 100mm face; Stow 16 –
Beams 2,508 3,700mm 150 × 50mm section 2,500kg
Beams 180 2,800mm 100 × 50mm section 2,000kg
Beams 180 2,000mm 80 × 50mm section 2,000kg

Link 51 M-duty Four-metre frames with mesh decking

The Link 51 M-duty schedule comprised 72 frames measuring 4,000 × 1,100mm, together with 396 beams and 396 mesh decking panels.

Although the beams shared a 2,700mm length, they were recorded in two different sections and UDL groups. The mesh decking panels measured 1,350 × 1,100mm.

Link 51 M-duty: components recorded in the project schedule
Component Quantity Size Detail Recorded UDL
Frames 72 4,000 × 1,100mm (height × depth) – –
Beams 132 2,700mm 70 × 40mm section 500kg
Beams 264 2,700mm 85 × 40mm section 1,500kg
Mesh decking panels 396 1,350 × 1,100mm – –

Apex UK 12 Three beam groups and two mesh sizes

The Apex UK 12 section comprised 78 frames at 4,000 × 1,100mm, with 432 beams and 432 mesh decking panels.

Its schedule included two groups of 2,700mm beams and a shorter 1,850mm group. Mesh decking panels were recorded in both 1,350 × 1,100mm and 900 × 1,100mm sizes.

Apex UK 12: components recorded in the project schedule
Component Quantity Size Detail Recorded UDL
Frames 78 4,000 × 1,100mm (height × depth) – –
Beams 132 2,700mm 50 × 50mm hollow section 500kg
Beams 264 2,700mm 100 × 50mm section 1,500kg
Beams 36 1,850mm 60 × 50mm section 500kg
Mesh decking panels 396 1,350 × 1,100mm – –
Mesh decking panels 36 900 × 1,100mm – –
An aisle of pallet racking with blue uprights, orange beams and wire mesh decks in the former GAME warehouse.
Racking with orange beams and wire mesh decks, photographed along an aisle. The schedule records mesh decking for both four-metre systems.

Trying to work out which system is in your own warehouse? Our pallet racking identifier covers the details that tell one manufacturer’s racking from another.

Project photographs

All eleven photographs from the project. Select any photograph to view it larger.

Planning a warehouse racking project in Basingstoke?

If you are planning pallet racking removal in Basingstoke, or another Hampshire warehouse project, send us photographs, the site postcode and a summary of what needs to change.

Include the racking manufacturer if known, approximate frame heights, beam lengths and any access or programme requirements. These details help us assess the project and discuss the next step.

Discuss a Racking Takedown Plan a Used Racking Installation

Or call 01827 949222

More from Rack It Stack It: all projects and case studies, our pallet racking removal and dismantling and pallet racking installation services, and how to sell used pallet racking.